CMS Trigger Meeting Nov. 6, 2001
at CERN, Bat. 40 2-A01

09:00 - 09:20 Trigger Installation - W. Smith
09:20 - 09:30 RPC Trigger Status - G.Wrochna
09:30 - 09:40 RPC Trigger LHC-like beam test - J.Krolikowski
09:40 - 10:00 DT Trigger Server - F. Odorici
10:00 - 10:20 DT Track Finder - J. Ero

10:20 - 10:40 BREAK

10:40 - 11:00 CSC Port Card & Optical Tests - P. Padley
11:00 - 11:20 CSC Track Finder - J. Hauser
11:20 - 11:40 GMT Update - H. Sakulin
11:40 - 12:00 Updated L1 mu+calo rates - J. Mumford
12:00 - 12:20 Global Trigger - C. Wulz

12:20 - 14:00 LUNCH

14:00 - 14:20 HCAL Trigger Primitives - C. Tully
14:20 - 14:40 ECAL Endcap Trigger Towers - D. Cussans
14:40 - 15:00 Synchronization Boards - J.C. da Silva
15:00 - 15:20 Cal Regional Trigger Status - S. Dasu
15:20 - 15:30 Cal Global Trigger Status/Plans - G. Heath
15:30 - 15:40 Cal Global Trigger Hardware - D. Machin
15:40 - 16:00 Trigger Control/Partitions - J. Varela

16:00 - 16:20 BREAK

16:20 - 16:40 Cal Trigger Simulation - P. Chumney
16:40 - 17:00 L1 for qqH->bb + 2 tag jets - F. Di Lodovico
17:00 - 17:20 L1 for qqH->(inv.) + 2 tag jets - S. Dasu
17:20 - 18:00 DISCUSSION: Staging & Installation Issues.
(also see talk on tag jets & HF trigger tower size by A.Nikitenko)
(also see reduced L1 muon acceptance talk by D. Acosta)

For a discription of the racks and the rack layout please see:
http://cmsdoc.cern.ch/~wogei/tc/rack_system/rack_system.html
http://cmsdoc.cern.ch/~wsmith/USC55_racks.html - official layout
http://cmsdoc.cern.ch/~wsmith/USC55_racks_v30.html - proposed layout
 


CMS Trigger Software Working Group
Nov. 7, 2001 at CERN, 9:00 - 13:00 Bat. 40 5-A01

Introduction - Joao Varela:
1. Tasks assigned to the Trigger Software WG
2. Working group organization:
   sub-system representatives and software developers
3. Identification of short/medium term 'collective tasks'
   and assignment to individuals/groups
BREAK
4. FE Electronics configuration w/ PVSS II - F. Glege
5. The XML based configuration and control of XDAQ - J. Gutleber
6. HCAL experience with using the ACE package - C. Tully
7. Hardware Access Library - C. Schwick


CMS CPT Plenary Talks
Nov. 8, 2001 at CERN, 9:00  Bat. 40 S2-A01
Cal Trigger Simulation - P. Chumney
Trigger Software Working Group - J. Varela



CPT Week Meeting Schedule